Lower Roswell Road Construction Update
Posted: 09.16.2011
Here's a brief update that we received from the project manager for the Lower Roswell Project (D6140)
Phase 1:
Davidson Road to Waterford Green/start of National Park
Start construction October 2011, Completion October 2012
Phase 2:
Waterford Green/start of National Park to Timber Ridge Road/Fulton County line
Start construction, contingent upon approval of National Park permit, approximately March 2012
Completion, 1 year construction duration, approximately March 2013
For additional information and project drawings, go to the official project website.