Lower Roswell Road Construction Update

Posted: 09.16.2011

Here's a brief update that we received from the project manager for the Lower Roswell Project (D6140)

Phase 1:
Davidson Road to Waterford Green/start of National Park

Start construction October 2011, Completion October 2012

Phase 2:
Waterford Green/start of National Park to Timber Ridge Road/Fulton County line

Start construction, contingent upon approval of National Park permit, approximately March 2012

Completion, 1 year construction duration, approximately March 2013

For additional information and project drawings, go to the official project website.