This information comes directly from the Cobb DOT:
1. Preliminary design work is underway and will take another 6 months, followed by 6 months of right of way and easement acquisition. Environmental documentation for the National Park will proceed concurrently, and will also take 8 to 12 months.
2. The project is scheduled to bid in October of 2010.
3. Construction should take 18 months